Injection Molding Part Cost Calculator

Estimate the cost of one accepted molded part after tooling allocation, setup, material, process, direct labor, expected scrap and secondary operations. This tool models molding economics only; it does not compare 3D printing.

01

Injection molding cost inputs

Allocate tooling and setup across quantity, then adjust manufacturing cost for accepted yield.

MODELED EXAMPLE — these defaults are not a supplier quote or market average. Replace them with your tooling quote and process records.

See how volume changes cost per part.

Modeled results using the current inputs. They are not measured production data or supplier quotes.

Good partsTooling / partEffective part costTotal production cost
100$100.00$110.96$11,095.56
500$20.00$26.96$13,477.78
1,000$10.00$16.46$16,455.56
5,000$2.00$8.06$40,277.78
10,000$1.00$7.01$70,055.56

Build a cost per accepted part, not a price guess.

Tooling and setup are allocated by quantity

Use the portion of tooling and one-time setup that belongs to this production plan. If a mold will support several products or future runs, document the allocation rule instead of charging the entire tool to one order without explanation.

Manufacturing inputs belong on the same basis

Material, molding process and direct labor should describe one produced part before scrap. Process cost may come from cycle time multiplied by a press rate, or from a supplier's stated unit charge. Do not add the same labor or machine time twice.

Secondary operations apply after accepted yield

The model treats trimming, inserts, inspection, finishing and packaging as a per-good-part input. If an operation is consumed before rejection, include it in the manufacturing base so the scrap adjustment applies.

base manufacturing cost = material + molding process + direct laborscrap-adjusted manufacturing cost = base manufacturing cost ÷ (1 − scrap rate)effective part cost = tooling ÷ quantity + setup ÷ quantity + scrap-adjusted manufacturing cost + secondary operationstotal production cost = effective part cost × required good parts

The model excludes finance cost, tax treatment, freight, storage, mold maintenance, design revisions and unplanned downtime unless you deliberately include them in an input. It also assumes the entered scrap rate applies uniformly to the run.

Know what the cost model does not know.

Should quoted unit price go in process cost?

Only if the quote excludes material and other fields you enter separately. Match the supplier's scope to the model so the same cost is not counted twice.

How should mold maintenance be included?

If maintenance is expected per run, add it to setup. If it scales with accepted quantity, convert it to a per-part amount. Keep the rule visible in your quote notes.

What quantity should I enter?

Use good parts expected from the evaluated run, not gross shots. Test more than one demand scenario because tooling allocation is very sensitive to volume.

When is the result likely to be wrong?

It can miss multi-cavity differences, changing cycle time, stepped supplier pricing, resin price changes, trial runs, rejected batches, mold life limits and costs outside the chosen boundary.

Compare methods only after the molded unit model is clear.

Carry the effective molded part cost into the break-even calculator, contrast it with a complete FDM cost, or inspect the anonymized quote case for a documented-input workflow.

See the source of each input, the formula, and the limit of the result.

Your slicer, invoices, energy tariff, and job records are the preferred inputs. Manufacturer documents support settings and specifications. Example defaults are editable assumptions that demonstrate the model—not measured results.

Preferred input
Your job records
Verification
Visible formula + unit checks
Defaults
Editable example assumptions
Output use
Planning comparison